[sci.space.shuttle] Shuttle Status for 12/07/90

yee@trident.arc.nasa.gov (Peter E. Yee) (12/08/90)

            KSC SHUTTLE STATUS REPORT - FRIDAY, DEC. 7, 1990  10:25 A.M.


                             STS-35 - COLUMBIA (OV 102)

               Work continues at Hangar AF on Cape Canaveral Air Force Sta-
          tion to disassemble the two solid rocket boosters.  Scheduled ac-
          tivities  today  and  into  the weekend include aft skirt removal
          and preparations for shipping and refurbishment.

               Landing is planned for Dec.  11 at about 11:25 p.m.  EST  on
          the Rogers Dry Lake Bed at Edwards Air Force Base,  Calif.  About
          five days of turnaround operations are planned before the orbiter
          is returned to KSC atop the 747 Shuttle Carrier Aircraft. Because
          the Astro-1 payload will still be in the payload bay, thus adding
          weight,  this ferry flight will include  provisions  for  several
          refueling stops enroute to KSC.


                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               The orbiter is scheduled to be powered up later today. Tacan
          activation  and self-test will continue through tonight.  Forward
          yoke installation work continues, as does tile maintenance work.

               Hydraulic water spray boiler checkouts  are  scheduled  over
          the weekend, as are checkouts of the main propulsion system (MPS)
          helium  system  and the Ku-band antenna.  Leak and pressurization
          tests on various lines in the  iquid  hydrogen  system  are  also
          scheduled.

               Several  brazing  operations were completed overnight on the
          main propulsation system.  Installation of  electronic  boxes  on
          cold  plates  continues.  At  the Hypergolic Maintenance Facility
          (HMF),  screen tests of the right-hand orbital manuevering system
          (OMS) continue. Final manifold drain is scheduled for next week.

                       STS-37 - Atlantis (OV 104) - OPF Bay 2

               Testing  of the main propulsion system continues.  Low pres-
          sure  pump  torque  checks  were  accomplished  overnight.  Waste
          management systems servicing has also been completed.

               The three main engines are scheduled to be removed next Wed-
          nesday  and Thursday.  Preparations are in work to move the left-
          hand OMS pod to the HMF tonight  for  required    flight-interval
          maintenance.

               Auxiliary  power  unit  (APU)  lube  oil  servicing  is also
          planned.  Smoke detection and fire suppression system  functional
          tests  have  begun and fire suppression equipment has checked out
          well.

                         STS-39 SOLID ROCKET BOOSTERS - VAB

               Stacking operations continue.  Range safety  ground  support
          equipment validations are scheduled for next week.