[sci.space.shuttle] Shuttle Status for 01/09/91

yee@trident.arc.nasa.gov (Peter E. Yee) (01/10/91)

            KSC SHUTTLE STATUS REPORT - WEDNESDAY, JAN. 9, 1990  10 a.m.


                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Leak and functional tests of the three auxiliary power units
          are planned.  Checkout of the  forward  reaction  control  system
          (FRCS)  is  continuing.  Checks of the orbital maneuvering system
          pods are underway.  Tests of the power reactant storage and  dis-
          tribution system are scheduled.  Heat shields are being installed
          around the main engines.   Tests of the closed circuit television
          system were completed.

               Interface  tests  between  the  Critical Ionization Velocity
          system and the Chemical Release Observation have been  completed.
          These  experiments  already installed in the payload bay are part
          of the Infrared Background Signature  Survey  for  the  Strategic
          Defense Initiative.

               Discovery  is being prepared for rollover to the Vehicle As-
          sembly Building the end of this month.


                       STS-37 - ATLANTIS (OV 104) - OPF BAY 2

               Tests of the remote  manipulator  system  were  successfully
          completed. Leak and functional tests of the auxiliary power units
          are continuing. Tests of the power reactant storage and distribu-
          tion  system  and of the orbiter's instrumentation system are un-
          derway.  Preparations are underway to replace windows 1 and 6 be-
          cause of blemishes. Hydraulic systems operations are planned this
          week.  Atlantis is being readied for launch scheduled in April.

                          STS-40 - COLUMBIA (OV 102) - VAB

               Technicians  are  performing  post-flight  work  in the crew
          cabin.   Roll around tires were installed to allow cycling of the
          landing gear doors for tile operations.   Tile operations and in-
          spections of the hydraulic system are continuing.

               Columbia  will remain in the Vehicle Assembly Building until
          Discovery is ready to be transferred out of the  OPF  later  this
          month.

                         STS-37 SOLID ROCKET BOOSTERS - VAB

               Booster stacking operations are continuing. The left forward
          center  segment was mated to the left booster early this morning.
          Also this morning,  the left forward segment was  transferred  to
          the VAB.