KSC SHUTTLE STATUS REPORT - FRIDAY, JAN. 25, 1991 STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1 LAUNCH - FEBRUARY/MARCH 1991 WORK IN PROGRESS: - Leak tests of two orbital maneuvering system thrusters and checks of the nozzle to body welds on a third thruster. - New thermal barrier in cure in the nose landing gear area. - Potable water servicing. - Flush of the auxiliary power units lube oil system. - Connections of ordnance devices for the remote manipulator sys- tem. - Leak checks of the main engines' hot gas system. - Cycling of the aerosurfaces, brakes and main engine thrust vec- tor control system. WORK COMPLETED: - Crew hatch cycle and leak check. WORK SCHEDULED: - Structural leak checks of the orbiter this weekend. - Final payload bay door closure this weekend. - Closeouts to prepare for rollover to the Vehicle Assembly Building the end of the month. STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - OPF BAY 2 LAUNCH - APRIL 1991 WORK IN PROGRESS: - Potable water servicing. - Functional test of the waste containment system. - Ku-band antenna testing. - Installation of windows 1 and 6. - Main engine securing operations. - Nose cap installation preparations. - Hot lube oil flush of auxiliary power unit no. 2. - Preparations to install the forward reaction control system. - Brazing check valve 3 in the main propulsion system. - Flutter buffet instrumentation installation. WORK COMPLETED: - Nose cap installed last night. WORK SCHEDULED: - Main engine flight readiness test this weekend. - Installation of the forward reaction control system next week. STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - VAB HB 2 LAUNCH - MAY WORK IN PROGRESS: - Post flight inspections of the space shuttle main engines. - Cycles of the landing gear doors to accommodate thermal protec- tion system operations. - Thermal protection system work. WORK SCHEDULED: - Closeouts to ready the vehicle for transfer to the Orbiter Processing Facility next week. STS-37 SOLID ROCKET BOOSTERS/EXTERNAL TANK - VAB WORK IN PROGRESS: - Mating operations for the right forward segment. - Closeouts of all booster field joints. WORK SCHEDULED: - Mate of the right forward assembly to the booster next week.