[sci.space.shuttle] Shuttle Status for 01/25/91 #2

yee@trident.arc.nasa.gov (Peter E. Yee) (01/26/91)

                              KSC PAYLOAD STATUS REPORT
                                  January 25, 1991

          Mitch Varnes
          407/867-2468
          FTS 823-2468
          ----------------------------------------------------------------
                             STS-39 (Late February 1991)

          The STS-39 Payload Readiness Review  (PRR)  Flight  Certification
          Review (CFR) was held at KSC on January 24.  No major issues were
          raised during the meeting,  and all members of the STS-39 payload
          community agreed that the payloads are ready to be transported to
          the  launch  pad.     CLOUDS-1A  and  RME-III  are  situated   in
          Discovery's  mid-deck  in the Orbiter Processing Facility.   CRO,
          CIV and MPEC are also in the OPF and mounted inside  the  forward
          section of Discovery's payload bay.   AFP-675, IBSS and STP-1 are
          in the Vertical Processing Facility and scheduled to be taken  to
          Pad 39-A on or about February 3.


                               STS-42 (December 1991)
                        International Microgravity Laboratory

          Checkout  and testing of the IML-1 elements is proceeding at Test
          Stand 2 of the Operations & Checkout Building High Bay.   Instal-
          lation  of  the IML-1 floor and experiment rack into the Spacelab
          module is underway.   The Spacelab's aft end cone is scheduled to
          be moved to Test Stand 2 within the next two weeks.


                                 STS-45 (March 1992)
                                       ATLAS-1

          Buildup and integration of the ATLAS-1 payload is underway in the
          Level IV area of the O&C High Bay.   The payload is being readied
          for its first powered-up test on February 4.