[sci.space.shuttle] Shuttle Status for 01/28/91

baalke@mars.jpl.nasa.gov (Ron Baalke) (01/29/91)

[Note:  Peter Yee is on travel, and I will be posting the NASA updates
        during his absence............Ron Baalke]
 
                  KSC SHUTTLE STATUS REPORT - MONDAY, JAN. 28, 1991
 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                            LAUNCH - FEBRUARY/MARCH 1991
 
          WORK IN PROGRESS:
          - Assessment of tests of two orbital maneuvering system thrusters
          and  inspections of the nozzle to body welds on a third thruster.
          - Checks of the flipper doors and elevons.
          - Cleaning of the payload bay.
          - Closeouts of the aft compartment.
 
          WORK COMPLETED:
          - Leak tests of two orbital maneuvering system thrusters and weld
          checks of a third thruster.
          - Connections of ordnance devices for the remote manipulator sys-
          tem.
          - Auxiliary power unit lube oil flush.
 
          WORK SCHEDULED:
          - Structural leak checks of the orbiter in the next few days.
          - Final payload bay door closure as early as tonight.
          - Closeouts to prepare  for  rollover  to  the  Vehicle  Assembly
          Building the end of the month.
 
          CONCERNS:
          -  Thruster  leak  rate  and  nozzle  to  body  welds  of another
          thruster. Possible replacement of thrusters.
 
            STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - OPF BAY 2
                                 LAUNCH - APRIL 1991
 
          WORK IN PROGRESS:
          - Main engine flight readiness test.
          - Water spray boiler leak and functional tests.
          - Hot lube oil flush of auxiliary power unit no. 2.
          - Preparations to install the forward reaction control system.
          - Flutter buffet instrumentation installation.
          - Potable water servicing.
          - Functional test of the waste containment system.
          - Ku-band antenna testing.
 
          WORK COMPLETED:
          - Brazing check valve 3 in the main propulsion system.
          - Hot lube oil flush of auxiliary power unit 1 complete.
          - Controller checks of APUs 1 and 2.
 
          WORK SCHEDULED:
          - Installation of the forward reaction control system this week.
          - Installation of windows 1 and 6 this week.
 
 
           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - VAB HB 2
                                    LAUNCH - MAY
 
          WORK IN PROGRESS:
          - Replacement of an instrumentation cable in avionics bay 1.
          - Wing strut mold impressions.
 
          WORK SCHEDULED:
          - Closeouts to ready the vehicle  for  transfer  to  the  Orbiter
          Processing Facility following Discovery's move to the VAB.
 
 
                  STS-37 SOLID ROCKET BOOSTERS/EXTERNAL TANK - VAB
 
          WORK IN PROGRESS:
          - Stacking the right forward assembly to the booster.
          - Closeouts of all booster field joints.
 
          WORK SCHEDULED:
          - Alignment of the boosters.
          -  Mate  of  the  external  tank to the boosters as early as this
          weekend.
 
          WORK COMPLETED:
          - Connecting the right forward segment to the stack.
 
      ___    _____     ___
     /_ /|  /____/ \  /_ /|      Ron Baalke         | baalke@mars.jpl.nasa.gov
     | | | |  __ \ /| | | |      Jet Propulsion Lab | 
  ___| | | | |__) |/  | | |___   M/S 301-355        | It's 10PM, do you know
 /___| | | |  ___/    | |/__ /|  Pasadena, CA 91109 | where your spacecraft is?
 |_____|/  |_|/       |_____|/                      | We do!