[sci.space.shuttle] Shuttle Status for 01/30/91

baalke@mars.jpl.nasa.gov (Ron Baalke) (01/31/91)

                KSC SHUTTLE STATUS REPORT - WEDNESDAY, JAN. 30, 1991
 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                                 LAUNCH - MARCH 1991
 
          WORK IN PROGRESS:
          - Preparations to replace three thrusters on orbital  maneuvering
          system pods.
          - Main propulsion system gaseous hydrogen system leak checks.
          - Cleaning of the payload bay.
          - Closeouts of the aft compartment.
          - Checks of the inboard flipper doors.
 
          WORK COMPLETED:
          - Checks of three orbital maneuvering system thrusters at the Hy-
          pergolic Maintenance Facility to be installed on Discovery.
          - Main propulsion system gaseous oxygen system leak checks.
 
          WORK SCHEDULED:
          - Installation of three OMS thrusters on Thursday.
          - Structural leak checks of the orbiter in the next few days.
          - Final payload bay door closure tonight.
          -  Closeouts  to  prepare  for  rollover  to the Vehicle Assembly
          Building next week.
 
          CONCERNS:
          - Two thrusters on the left pod will be replaced because  of  out
          of  specification leakage.  One thruster on the right pod will be
          replaced because of suspect nozzle to body welds.  New  thrusters
          have  been  checked  and will be delivered to the OPF today.  Re-
          placement operations are scheduled to begin at midnight and  will
          continue  through  tomorrow.  Thruster connections and retest ac-
          tivities are scheduled to be complete by Sunday.  Rollover to the
          VAB is targeted for Feb. 7.
 
            STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - OPF BAY 2
                                 LAUNCH - APRIL 1991
 
          WORK IN PROGRESS:
          - Water spray boiler leak and functional tests.
          - Auxiliary power unit functional tests.
          - Preparations to install the forward reaction control system.
          - Potable water servicing.
          - External tank door latch pull test.
 
          WORK COMPLETED:
          - Installation of the main engine 2 controller.
          - Forward reaction control system arrived at OPF last night.
          - Ku-band antenna testing.
 
          WORK SCHEDULED:
          - External tank door functional test tomorrow.
          - Main engine 2 flight readiness test next week.
          - Installation of heat shields for engines 1 and 3.
          - Installation of the forward reaction control system tonight.
          - Installation of windows 1 and 6 this week.
 
 
           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - VAB HB 2
                                    LAUNCH - MAY
 
          WORK IN PROGRESS:
          - Installation of wing struts.
          -  Modification to          the middeck.
          - Thermal protection system operations.
          - Cycling of the landing gear doors for tile operations.
 
          WORK SCHEDULED:
          - Closeouts to ready the vehicle  for  transfer  to  the  Orbiter
          Processing Facility following Discovery's move to the VAB.
 
 
                  STS-37 SOLID ROCKET BOOSTERS/EXTERNAL TANK - VAB
 
          WORK IN PROGRESS:
          - Closeouts of all booster field joints and cable routing.
 
          WORK SCHEDULED:
          - Alignment of the boosters.
          - Mate of the external tank to the boosters as early as Monday.

      ___    _____     ___
     /_ /|  /____/ \  /_ /|      Ron Baalke         | baalke@mars.jpl.nasa.gov
     | | | |  __ \ /| | | |      Jet Propulsion Lab | 
  ___| | | | |__) |/  | | |___   M/S 301-355        | It's 10PM, do you know
 /___| | | |  ___/    | |/__ /|  Pasadena, CA 91109 | where your spacecraft is?
 |_____|/  |_|/       |_____|/                      | We do!