yee@trident.arc.nasa.gov (Peter E. Yee) (02/07/91)
                 KSC SHUTTLE STATUS REPORT - WEDNESDAY, FEB. 6, 1991
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                                 LAUNCH - MARCH 1991
          WORK IN PROGRESS:
          - Retest of a replaced heater wire for thruster R3A.
          - Preparations for the positive pressure structural leak test.
          - Vehicle closeouts in preparation for transfer to the VAB.
          - Closeouts of the flipper doors which protect  elevon  actuators
          and hinges.
          WORK COMPLETED:
          - Repair of the heater wire for thruster R3A.
          - Replacement of the left hand nose landing gear tire and top off
          of the tire pressure.
          -  Replacement of the thermal barrier near the left external tank
          door foward hinge.
          WORK SCHEDULED:
          - Structural leak checks of the orbiter later today.
          - Weight and center of gravity checks.
          - Rollover to the Vehicle Assembly Building targeted for Feb. 9.
            STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - OPF BAY 2
                                 LAUNCH - APRIL 1991
          WORK IN PROGRESS:
          - Water spray boiler leak and functional tests.
          - Main engine leak tests.
          - Installation of heat shields around main engines.
          - Auxiliary power unit leak and functional tests.
          WORK COMPLETED:
          - Window 6 was installed.
          - Checks of the closed circuit television system.
          WORK SCHEDULED:
          - Tests of the right orbital maneuvering system pod.
          - Tests of the forward reaction control system.
          - Engine 2 flight readiness test tomorrow.
          - Ammonia boiler servicing tonight.
           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - VAB HB 2
                                    LAUNCH - MAY
          WORK IN PROGRESS:
          - Closeouts of the orbiter.
          WORK COMPLETED:
          - Extension of the landing gears in preparation for the  move  to
          the OPF.
          WORK SCHEDULED:
          -  Closeouts  to  ready  the  vehicle for transfer to the Orbiter
          Processing Facility several hours after Discovery's move  to  the
          VAB.
                  STS-37 SOLID ROCKET BOOSTERS/EXTERNAL TANK - VAB
          WORK IN PROGRESS:
          - Closeouts of the liquid hydrogen umbilical.
                             STS-39 BOOSTERS/TANK - VAB
          WORK IN PROGRESS:
          - Preparations to mate the orbiter Discovery Saturday.
          - Final walkdown for mate.
          WORK SCHEDULED:
          - Retraction of platforms away from the vehicle elements.
          - Mating the orbiter Saturday.