[sci.space.shuttle] Shuttle Status for 02/14/91

yee@trident.arc.nasa.gov (Peter E. Yee) (02/19/91)

           KSC SHUTTLE STATUS REPORT - THURSDAY, FEB. 14, 1991 - 9:30 a.m.


                        STS-39/DoD - DISCOVERY (OV 103) - VAB
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Power down the orbiter and prepare to roll to the launch pad.

          WORK SCHEDULED:
          - Rollout to Launch Pad 39-A targeted for Friday at 12:01 a.m.
          - Install payload in Discovery's payload bay Saturday.
          - Terminal Countdown Demonstration Test Feb. 19-20.
          - Flight Readiness Review Feb. 26-27.
          - Replacement of the load control assembly (LCA),  the electronic
          box in the aft compartment, which controls the power load for the
          orbital maneuvering system thruster heaters.  Rails used to lower
          the unit out of the aft compartment were not  in  place  by  late
          yesterday  when  power  up  was  scheduled.  Officials decided to
          proceed on with planned power up tests,   reconnect the  old  LCA
          unit and replace it on Sunday.

          WORK COMPLETED:
          -  Electrical monoball connections between the orbiter and exter-
          nal tank.
          - Critical parts of the Shuttle Interface Test.


            STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - OPF BAY 2
                                 LAUNCH - APRIL 1991

          WORK IN PROGRESS:
          - Tests of the left and right orbital maneuvering system pods.
          - Leak tests of a bellows on water spray boiler no. 2.
          - Inspections of the elevons.

          WORK COMPLETED:
          - Tests of the air data systems and  of  the  Microwave  Scanning
          Beam Landing System.

          WORK SCHEDULED:
          -  Borescope inspections of the thrusters on the forward reaction
          control system and the left orbital maneuvering system pod.
          -  Connections  of  the  crossfeed  lines  between  the   orbital
          maneuvering system pods tonight.



           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1
                                    LAUNCH - MAY


          WORK IN PROGRESS:
          - Removal of the Astro payload.
          -  Preparations  to remove heat shields around the three main en-
          gines.
          - Sampling the orbiter's hydraulic fluid.
          - Flush of the waste containment system.

          WORK COMPLETED:
          - Functional test of the payload bay doors.

          WORK SCHEDULED:
          - Radar altimeter test tomorrow.
          - Removal of the three main engines next week.