[sci.space.shuttle] Shuttle Status for 02/19/91

yee@trident.arc.nasa.gov (Peter E. Yee) (02/20/91)

           KSC SHUTTLE STATUS REPORT - TUESDAY, FEB. 19, 1991 - 9:30 a.m.

                        STS-39/DoD - DISCOVERY (OV 103) - VAB
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Evaluation of cracks in hinges for the external tank right  and
          left doors. (See concerns.)
          -  Helium  signature leak test of the three main engines and main
          propulsion system.
          - Terminal Countdown Demonstration Test Feb.   began this morning
          and  will  culminate  with  a  simulated engine cutoff at 11 a.m.
          tomorrow.
          - Interface verification tests between the payload  and  the  or-
          biter.
          - Retest of the load control assembly.

          WORK COMPLETED:
          -  Installation  of  the  STS-39  payload into Discovery's bay on
          Saturday.
          - Replacement of the load control assembly, the electronic box in
          the aft compartment,  which controls the power load for the orbi-
          tal maneuvering system thruster heaters.
          - STS-39 flight crew arrived yesterday morning.
          - Successful tests of the new gaseous nitrogen hydrogen dispersal
          system on the mobile launcher platform.

          WORK SCHEDULED:
          - Flight Readiness Review Feb. 26-27.

          CONCERNS:
          -  During closeout inspections of Discovery's external tank doors
          yesterday morning, several cracks were discovered.  There are two
          hinges  per door.  Cracks have been detected in three of the four
          hinges.  Two of the cracks have been described as being 2  inches
          long  by  approximately  one-tenth  inch wide.  Engineers will be
          evaluating data over the next few  days  to  determine  the  best
          course of action.

            STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - OPF BAY 2
                                 LAUNCH - APRIL 1991

          WORK IN PROGRESS:
          - Install nose landing gear tires.
          - Thermal protection system operations.
          - Inspections of the external tank door hinges.
          - Decay checks of the water spray boilers.
          -  Interface  verification  tests of the left orbital maneuvering
          system pod.

          WORK COMPLETED:

          - Electrical redundancy checks of the orbital maneuvering  system
          pods.

           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1
                                    LAUNCH - MAY

          WORK IN PROGRESS:
          - Removing heat shields from around the three main engines.
          - Inspections of the external tank door hinges.
          - Repairing the waste dump system.

          WORK SCHEDULED:
          - Removal of the three main engines this weekend.

          WORK COMPLETED:
          - Installed window no. 1.
          - Deserviced freon system.

                              VEHICLE ASSEMBLY BUILDING


          WORK SCHEDULED:
          -  STS-37  tank and solid rocket booster stack on mobile launcher
          platform 1 was transferred from high bay 3 to high bay 1  yester-
          day.

          -  This  week,  mobile launcher platform 3 will be moved into VAB
          high bay 3,  which is directly across the transfer aisle from the
          external  tank  to be used on STS-40.  MLP 3 will be prepared for
          the STS-40 mission.