[sci.space.shuttle] Shuttle Status for 03/01/91

yee@trident.arc.nasa.gov (Peter E. Yee) (03/05/91)

            KSC SHUTTLE STATUS REPORT - FRIDAY, MAR. 1, 1991 - 9:30 a.m.

                       STS-39/DoD - DISCOVERY (OV 103) - PAD A
                           LAUNCH - LATE APRIL, EARLY MAY


          WORK IN PROGRESS:
          - Preparations for rolling back to the Vehicle Assembly  Building
          no earlier than 12:01 a.m. March 7.
          - Demate the orbiter midbody umbilical unit.
          - Payload electrical demates.

          WORK SCHEDULED:
          - Disconnection of ordnance devices on Monday.
          -  Transferring  the  STS-39  Air  Force Program 675 payload from
          Discovery's payload bay to the Payload Changeout Room on Monday.
          - Offloading hypergolic propellants from the orbital  maneuvering
          system and reaction control system on Tuesday.

          CONCERNS:
          -  Shuttle officials decided yesterday to roll Discovery back for
          repairs to the cracked hinges for  the  external  tank  umbilical
          door  drive  mechanism.  Repairs  will  be  made  in  the Orbiter
          Processing Facility.


            STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - OPF BAY 2
                                   LAUNCH - APRIL


          WORK IN PROGRESS:
          - Preparations for rollover to the VAB on March 6.
          - Thermal protection system operations.
          - Closeouts of the midbody in preparation  for  rollover  to  the
          VAB.
          - Positive pressure tests of the vehicle.
          - Installation of wing struts.

          WORK COMPLETED:
          - Successful tests of the thruster on the right orbital maneuver-
          ing system pod.
          - Checks of water spray boiler no. 2.

          WORK SCHEDULED:
          - Payload bay door closure this weekend.
          - Transfer of the vehicle to the Vehicle Assembly Building on
          March 6.



           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1
                                    LAUNCH - MAY



          WORK IN PROGRESS:
          - Tests of the power reactant storage and distribution system.
          -  Offloading  residual  hypergolic  propellant  from the orbital
          maneuvering system and reaction control system.
          - Preparations to deservice freon.
          - Preparations to drain the auxiliary power unit catch bottles.
          - Checks of the main propulsion system.
          - Installation of the environmental control system dump nozzle.
          - Replacement of the payload bay door environmental seal.