[sci.space.shuttle] Shuttle Status for 03/05/91

yee@trident.arc.nasa.gov (Peter E. Yee) (03/06/91)

             KSC SHUTTLE STATUS REPORT - TUESDAY, MAR. 5, 1991 - 10 a.m.


            STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - OPF BAY 2
                                   LAUNCH - APRIL


          WORK IN PROGRESS:
          - Preparations for roll over to the VAB late on March 7 or  early
          the next day.
          - Closeouts of the midbody and aft compartment in preparation for
          rollover to the VAB.
          - Positive pressure tests of the vehicle.
          -  Troubleshooting  of  noise  on main power bus A.  Intermittent
          spikes occurred when the orbiter's hydraulic system was being ac-
          tivated this weekend.

          WORK COMPLETED:
          - Aft positive pressure test.

          WORK SCHEDULED:
          - Transfer of the vehicle to the Vehicle Assembly Building on
          March 7 or 8.

          CONCERNS:
          - Evaluation of a very small crack on each  of  the  forward  lug
          hinges  of  the left and right external tank umbilical door drive
          mechanisms is underway.  These cracks were found after evaluation
          of  several dye penetrant tests and borescope inspections.  Addi-
          tional dye penetrant tests are underway today to recheck all four
          lug hinges. A resolution is expected before the orbiter is trans-
          ferred to the VAB.

                       STS-39/DoD - DISCOVERY (OV 103) - PAD A
                           LAUNCH - LATE APRIL, EARLY MAY


          WORK IN PROGRESS:
          - Preparations for rolling back to the Vehicle Assembly  Building
          no earlier than 2 a.m. March 7.
          -  Offloading hypergolic propellants from the orbital maneuvering
          system and reaction control system on Tuesday.

          WORK COMPLETED:
          - Disconnection of ordnance devices.
          - Transferring the STS-39 Air  Force  Program  675  payload  from
          Discovery's payload bay to the Payload Changeout Room on Monday.



           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1
                                    LAUNCH - MAY

          WORK IN PROGRESS:
          - Filling and bleeding of the orbiter's hydraulic system.
          - Tests of the power reactant storage and distribution system.
          -  Offloading  residual  hypergolic  propellant  from the orbital
          maneuvering system and reaction control system.
          - Preparations to drain the auxiliary power unit catch bottles.
          - Checks of the main propulsion system helium system.
          - Installation of the environmental control system dump nozzle.
          - Replacement of the payload bay door environmental seal.
          - Replacement of a radiator controller.