[sci.space.shuttle] Shuttle Status for 03/08/91

yee@trident.arc.nasa.gov (Peter E. Yee) (03/09/91)

          KSC SHUTTLE STATUS REPORT - FRIDAY, MAR. 8, 1991 - 9:30 a.m.

            STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - OPF BAY 2
                                   LAUNCH - APRIL

          WORK IN PROGRESS:
          - Preparations for roll over to the VAB targeted late afternoon.
          - Orbiter transporter operations.

          WORK COMPLETED:
          - Weight and center of gravity determination.
          - Application of korpon corrosive protectant paint
	    on the lug hinge area.

          WORK SCHEDULED:
          - Mating Atlantis to the external tank this weekend.
          - Rollout to Launch Pad 39-B no earlier than March 14.

                        STS-39/DoD - DISCOVERY (OV 103) - VAB
                           LAUNCH - LATE APRIL, EARLY MAY

          WORK IN PROGRESS:
          - Putting platforms in place around the vehicle.
          - Demate preparations.

          WORK COMPLETED:
          - Rollback from the launch pad.  Discovery was hard down  in  the
          VAB by 11:30 a.m. yesterday.

          WORK SCHEDULED:
          - Demate is planned next week after Atlantis is mated.
          - Transfer to the OPF is planned next week.

           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1
                                    LAUNCH - MAY

          WORK IN PROGRESS:
          - Removal of the external tank umbilical door drive mechanism lug
          hinges  for  shipment  to  the Rockwell plant in California.  The
          hinges will be beefed up and sent back to KSC for installation.
          - Tests of the power reactant storage and distribution system.
          - Offloading residual  hypergolic  propellant  from  the  orbital
          maneuvering system and reaction control system.
          -  Replacement  of the helium check valves in the main propulsion
          system.
          - Tests of the thrust vector control system.
          - Hot oil flush of the auxiliary power units.

          WORK COMPLETED:
          - X-rays of brazes  of  the  environmental  control  system  dump
          nozzle.