baalke@mars.jpl.nasa.gov (Ron Baalke) (03/14/91)
KSC SHUTTLE STATUS - WEDNESDAY, MARCH 13, 1991 --- 10:30 a.m. _________________________________________________________________ STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - VAB HB 3 LAUNCH -- EARLY APRIL WORK IN PROGRESS: * Orbiter Interface verification tests * Tile step and gap operations near nose cone * SRB battery checks * Vehicle frequency response test * Preparations for rollout to pad 39-B * Platform retractions in VAB * GRO integration into Payload Changeout Room at pad B (arrived at pad at 4:00 a.m. today) WORK COMPLETED: * Liquid oxygen and liquid hydrogen monoball electrical connections * Leak checks of main propulsion system * Hydraulic circulation and sample tests * Removal of debris shields * SRB APU checks WORK SCHEDULED: * Rollout to pad 39-B targeted for 12:01 a.m. Friday * Following rollout to pad: - APU hot fire (Friday) - Payload installation into orbiter payload bay (Sunday) - Helium Signature test (Monday) - Terminal Countdown Demonstration Test (T-0 on Wednesday) STS-39/DoD - DISCOVERY (OV 103) - VAB HB 1 LAUNCH -- LATE APRIL, EARLY MAY WORK IN PROGRESS: * Lifting orbiter to transfer aisle WORK COMPLETED: * Installation of aft access doors * Sling lift and build up and orbiter demate operations WORK SCHEDULED: * VAB orbiter hydraulic operations * Replace flight nose wheel tire with rollover wheel tire in VAB transfer aisle * Rollover to Orbiter Processing Facility bay 2 Thursday morning at 8:30 a.m. * Replace ET door hinge mechanism with one from Endeavour once in the Orbiter Processing Facility STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1 LAUNCH - MAY WORK IN PROGRESS: * Water Spray boiler servicing * Auxiliary power unit leak and functional tests * Mid-body operations * Thruster inspections WORK COMPLETED: * External tank umbilical door drive mechanism removed and shipped to Rockwell plant in California Saturday (due back at KSC end of March) * Freon loop reservicing operations * APU number 2 fuel line connections * APU lube hot oil flush WORK SCHEDULED: * OMS/FRCS functional and deservicing operations * Solid rocket booster stacking operations in VAB following STS-37 rollout operations ___ _____ ___ /_ /| /____/ \ /_ /| Ron Baalke | baalke@mars.jpl.nasa.gov | | | | __ \ /| | | | Jet Propulsion Lab | ___| | | | |__) |/ | | |___ M/S 301-355 | Change is constant. /___| | | | ___/ | |/__ /| Pasadena, CA 91109 | |_____|/ |_|/ |_____|/ |