[sci.space.shuttle] Shuttle Status for 04/08/91

yee@trident.arc.nasa.gov (Peter E. Yee) (04/09/91)

          KSC SHUTTLE STATUS REPORT - MONDAY, APR. 8, 1991 - 1:30  p.m.

           STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - FLIGHT DAY 4


          WORK IN PROGRESS:
          - Solid rocket booster disassembly operations.  

          WORK COMPLETED:
          - Launched April 5 at 9:22 a.m. EST.
          -  Tow  of  the  solid  rocket  boosters  in to Hangar AF on Cape
          Canaveral Air Force Station on Saturday.

          WORK SCHEDULED:
          - Landing on Wednesday,  at 10:34 a.m.  EDT,  Edwards  Air  Force
          Base, Calif.

                     STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                                   LAUNCH - APRIL

          WORK IN PROGRESS:
          -  Loading  of  hypergolic propellants into the orbiter's onboard
          storage tanks.
          - Reopening of the launch pad for normal work at about noon.

          WORK COMPLETED:
          - Installation of the STS-39 payloads  into  Discovery's  payload
          bay.
          - Payload to orbiter interface verification tests.

          WORK SCHEDULED:
          - Main engine flight readiness test Wednesday.  Engine valves are
          cycled and sensors are calibrated.
          - Start aft closeouts later this week.
          - Flight Readiness Review April 15-16.

           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1
                                    LAUNCH - MAY

          WORK IN PROGRESS:
          - Closeouts of the orbital maneuvering system pods.
          - Inspections of the radiators.
          - Spacelab closeouts.
          - Hatch functional test.
          - Tests of the S-band antenna.
          - Thermal protection system operations.

          WORK COMPLETED:
          - Installation of the Spacelab Life Sciences tunnel.
          - Crew Equipment Interface Test with flight crew this weekend.



                         STS-40 SOLID ROCKET BOOSTERS - VAB


          WORK IN PROGRESS:
          - Mating of the right aft center segment to the right booster.

          WORK COMPLETED:
          - Stacking of the left forward assembly to complete the left hand
          booster.

          WORK SCHEDULED:
          - Mating of the external tank to the solid rocket  boosters  next
          week.