yee@trident.arc.nasa.gov (Peter E. Yee) (04/11/91)
KSC SHUTTLE STATUS REPORT - TUESDAY, APR. 9, 1991 - 10 a.m. STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - FLIGHT DAY 5 WORK IN PROGRESS: - Solid rocket booster disassembly operations. Hydrolasing opera- tions are underway to remove the thermal protection foam and cork from the boosters. WORK SCHEDULED: - Landing on Wednesday, at 10:34 a.m. EDT, Edwards Air Force Base, Calif. STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A LAUNCH - APRIL WORK IN PROGRESS: - Circulation and sampling of the hydraulic fluid in the orbiter's hydraulic system. - Servicing payloads. - Installation of booster thermal curtains. - Closeouts of the avionics bays. WORK COMPLETED: - Loading of hypergolic propellants into the orbiter's onboard storage tanks. - Pad reopened for normal work. - Payload bay doors opened. WORK SCHEDULED: - Main engine flight readiness test Wednesday. Engine valves are cycled and sensors are calibrated. - Start aft closeouts later this week. - Flight Readiness Review April 15-16. STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1 LAUNCH - MAY WORK IN PROGRESS: - Auxiliary power unit leak and functional tests. - Inspections of the radiators. - Hatch functional test. - Tests of the S-band antenna. - Thermal protection system operations. WORK COMPLETED: - Closeouts of Spacelab. STS-40 SOLID ROCKET BOOSTERS - VAB WORK IN PROGRESS: - Mating of the right forward center segment to the right booster. - Closing out the field joints for flight. WORK COMPLETED: - Stacking of the right aft center segment. WORK SCHEDULED: - Mating of the external tank to the solid rocket boosters next week.