[sci.space.shuttle] Shuttle Status for 04/09/91

yee@trident.arc.nasa.gov (Peter E. Yee) (04/11/91)

          KSC SHUTTLE STATUS REPORT - TUESDAY, APR. 9, 1991 - 10  a.m.

           STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - FLIGHT DAY 5


          WORK IN PROGRESS:
          - Solid rocket booster disassembly operations. Hydrolasing opera-
          tions are underway to remove the thermal protection foam and cork
          from the boosters.

          WORK SCHEDULED:
          - Landing on Wednesday,  at 10:34 a.m.  EDT,  Edwards  Air  Force
          Base, Calif.

                     STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                                   LAUNCH - APRIL

          WORK IN PROGRESS:
          -  Circulation  and  sampling  of  the  hydraulic  fluid  in  the
          orbiter's hydraulic system.
          - Servicing payloads.
          - Installation of booster thermal curtains.
          - Closeouts of the avionics bays.

          WORK COMPLETED:
          - Loading of hypergolic propellants into  the  orbiter's  onboard
          storage tanks.
          - Pad reopened for normal work.
          - Payload bay doors opened.

          WORK SCHEDULED:
          - Main engine flight readiness test Wednesday.  Engine valves are
          cycled and sensors are calibrated.
          - Start aft closeouts later this week.
          - Flight Readiness Review April 15-16.

           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1
                                    LAUNCH - MAY

          WORK IN PROGRESS:
          - Auxiliary power unit leak and functional tests.
          - Inspections of the radiators.
          - Hatch functional test.
          - Tests of the S-band antenna.
          - Thermal protection system operations.

          WORK COMPLETED:
          - Closeouts of Spacelab.



                         STS-40 SOLID ROCKET BOOSTERS - VAB


          WORK IN PROGRESS:
          - Mating of  the  right  forward  center  segment  to  the  right
          booster.
          - Closing out the field joints for flight.

          WORK COMPLETED:
          - Stacking of the right aft center segment.

          WORK SCHEDULED:
          -  Mating  of the external tank to the solid rocket boosters next
          week.