[sci.space.shuttle] Shuttle Status for 04/10/91

yee@trident.arc.nasa.gov (Peter E. Yee) (04/11/91)

          KSC SHUTTLE STATUS REPORT - WEDNESDAY, APR. 10, 1991 - 10  a.m.

           STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - FLIGHT DAY 6


          WORK IN PROGRESS:
          - Solid rocket booster disassembly operations. Hydrolasing opera-
          tions to remove the thermal protection foam  and  cork  from  the
          boosters.
          - KSC recovery team in position at Edwards.

          WORK SCHEDULED:
          -  Landing  scheduled  today  pending  favorable weather,  on the
          second opportunity,  at 12:12 p.m.  EDT,  Edwards Air Force Base,
          Calif.

                     STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                                   LAUNCH - APRIL

          WORK IN PROGRESS:
          - Main engine flight readiness test to cycle valves and calibrate
          sensors.

          WORK COMPLETED:
          -  Circulation  and  sampling  of  the  hydraulic  fluid  in  the
          orbiter's hydraulic system.
          - Servicing payloads.
          - Installation of booster thermal curtains.
          - Pad was cleared for several hours last  night  due  to  adverse
          weather.  A tornado was spotted near Playalinda Beach, just north
          of the launch pad.

          WORK SCHEDULED:
          - Start aft closeouts later this week.
          - First part of ordnance installation Friday.
          - Flight Readiness Review April 15-16.

           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1
                                    LAUNCH - MAY

          WORK IN PROGRESS:
          - Servicing the auxiliary power units with lube oil.
          - Inspections of the radiators.
          - Tests of the S-band antenna.
          - Thermal protection system operations.
          - Main engine thrust vector control systems checks.

          WORK SCHEDULED:
          - Final payload bay door closure.


                         STS-40 SOLID ROCKET BOOSTERS - VAB


          WORK IN PROGRESS:
          - Mating of the right forward segment to the right booster.
          - Closing out the field joints for flight.

          WORK COMPLETED:
          - Stacking of the right forward center segment.

          WORK SCHEDULED:
          - Mating of the external tank to the solid rocket  boosters  next
          week.