[sci.space.shuttle] Shuttle Status for 04/29/91

yee@trident.arc.nasa.gov (Peter E. Yee) (04/30/91)

          KSC SHUTTLE STATUS REPORT - MONDAY, APRIL 29, 1991 - 10:30 AM

                     STS-39/DoD - DISCOVERY (OV 103) - ON ORBIT


               Discovery was launched at  7:33:14.07812  a.m.  EDT  Sunday,
          April  28  after  a brief delay to analyze the sudden start of an
          onboard orbiter and payload recorder.  After a discussion,  offi-
          cials  determined  that  there  was no problem with the orbiter's
          computers and the  countdown was resumed.

               Landing is planned on Monday, May 6 at 2:57 p.m.  EDT at Ed-
          wards Air Force Base, Calif.

               Damage  to  the launch pad was reported as very minimal this
          morning.

               The solid rocket boosters are being towed  by  the  recovery
          ships to Hangar AF. They are scheduled to arrive at the Hangar at
          about  5  p.m.  today.  Safing the boosters is the first order of
          business.  Afterwards,  they will be inspected and  washed  down.
          Thermal foam and exterior cork will be removed with high pressure
          water.  Disassembly  operations  are  scheduled  to take about 10
          days.


              STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - VAB
                                     LAUNCH - MAY

          WORK IN PROGRESS:
          - Shuttle Interface Test began early this morning.

          WORK COMPLETED:
          - Orbiter Columbia mated to the external tank.
          - Electrical  and  mechanical  connections  between  the  vehicle
          elements and the launch platform.

          WORK SCHEDULED:
          - Rollout to Launch Pad 39-B targeted for 12:01 a.m. Thursday,
            May 2.
          - Terminal Countdown Demonstration Test May 6-7.
          - Flight Readiness Review planned May 13-14.


                       STS-43 - ATLANTIS (OV 104) - OPF BAY 2

          WORK IN PROGRESS:
          - Sniff checks of the orbital maneuvering system motor valves.
          -  Preparations to drain residual hypergolic propellants from the
          onboard storage tanks.
          - Auxiliary power unit lube oil service.
          - Preparations to remove the three main engines.
          - Stacking of the first booster segment, the left aft booster, in
          the VAB.

          WORK COMPLETED:
          - Removal of external tank umbilical housings.
          - Draining the waste management system.
          - Main engine drying operations.
          - Removal of the remote manipulator system.
          - Replacement of the no. 3 fuel cell.
          - Replacement of window no. 1.

          WORK SCHEDULED:
          - Removal of the three main engines late tomorrrow.


                        ENDEAVOUR (OV 105) - PALMDALE, CALIF.

               Endeavour is being prepared for delivery to KSC  this  week.
          The  new  orbiter  was  rolled  out of the Rockwell manufacturing
          plant on April 25.  Endeavour is scheduled to  be  mated  to  the
          agency's new 747 Shuttle Carrier Aircraft on Wednesday.

               The  first  leg  of  the  cross  country ferry flight,  from
          California to Texas,  is scheduled for May 2.  A refueling and an
          overnight  stop is planned at Ellington Field in Houston,  Texas.
          The journey,  from Texas to Florida,  will continue the next  day
          with the estimated time of arrival at KSC is midday.