[sci.space.shuttle] Shuttle Status for 05/08/91

yee@trident.arc.nasa.gov (Peter E. Yee) (05/09/91)

          KSC SHUTTLE STATUS REPORT - WEDNESDAY, MAY 8, 1991 - 11:30 AM

           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - PAD 39-B
                                     LAUNCH - MAY

          WORK IN PROGRESS:
          - Preparations to load hypergolic  propellants  onboard  the  or-
          biter. The pad will be cleared later tonight for this operation.
          - Launch Readiness Review  this afternoon.
          -  Inspections  of the Spacelab module for damage that could have
          been caused by a portable breathing unit that fell from the  for-
          ward structure of the module to the aft end. (See concerns.)

          WORK COMPLETED:
          - Calibration of the inertial measurement units.

          WORK SCHEDULED:
          -  Loading  hypergolic  propellants  into  the  orbiter's orbital
          maneuvering system and reaction  control  system  storage  tanks.
          Auxiliary  power  units  and solid rocket booster hydraulic power
          units will be serviced with hydrazine as part of  this  operation
          tomorrow.
          - Flight Readiness Review planned May 13-14.

          CONCERNS:
          -  The  emergency breathing unit weighs about 10-20 pounds and is
          about 12 by 12 inches.  An inspection of the module  is  underway
          today.  Officials  want  to understand how and when the unit came
          loose and fell. Initial inspections show no damage to the module.


                       STS-43 - ATLANTIS (OV 104) - OPF BAY 2

          WORK IN PROGRESS:
          - Auxiliary power unit leak and functional tests.
          - Power reactant storage and distribution system testing.
          - Tests of the Tacan system and the S-band antenna.
          - Checks of the main propulsion system helium system.
          - Thermal protection system operations.

          WORK COMPLETED:
          - Installation of the potty yesterday.



                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1


          WORK IN PROGRESS:
          - Offloading of residual propellant from the  fuel  cell  storage
          tanks. (Certain areas are cleared for this operation.)
          -  Installing access platforms in various areas including the aft
          compartment.

          WORK SCHEDULED:
          - Opening of the payload bay doors Friday.
          - Post flight inspections
          - Replacement of thermal barriers between tiles on the  orbiter's
          belly.  About  twice as many fillers as usual will have to be re-
          placed because of over-temperature conditions experienced  during
          this  particular re-entry.  Initial indications are that about 10
          tiles will  need  to  be  replaced  as  a  result  of  the  over-
          temperature conditions.



                       ENDEAVOUR (OV 105) - VAB Transfer Aisle

               Endeavour  was  towed to the Vehicle Assembly Building over-
          night arriving in the transfer aisle at approximately  3:30  a.m.
          today. The orbiter will be moved to high bay 2 on Friday where it
          will be jacked and leveled.  Next week,  the orbiter's weight and
          center of gravity will be determined.  Tail cone  removal  opera-
          tions are planned the end of next week.


                                     TURN BASIN

               Today,  external tank no.  52, earmarked for the STS-44 mis-
          sion in November,  is scheduled to arrive by barge in KSC's  turn
          basin at Complex 39.