KSC SHUTTLE STATUS REPORT - TUESDAY, MAY 14, 1991 - 10:30 AM
STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - PAD 39-B
LAUNCH - MAY 22
WORK IN PROGRESS:
- Launch countdown preparations.
- Purges of the external tank.
- Closeouts of the aft comparment.
- Closeouts of the solid rocket boosters.
WORK SCHEDULED:
- Final ordnance installation Thursday.
- Closing the aft compartment for flight Friday.
- Start launch countdown 5 p.m. EDT Saturday.
- STS-40 crew arrives 1:30 p.m. Sunday.
- Launch at 8 a.m. EDT Wednesday, May 22.
WORK COMPLETED:
- Flight Readiness Review held yesterday. No significant issues.
- Installation and testing of the two spacesuits for contigency
purposes.
STS-43/TDRS - ATLANTIS (OV 104) - OPF BAY 2
WORK IN PROGRESS:
- Preparations to remove the forward reaction control system.
- Auxiliary power unit (APU) leak and functional tests.
- Power reactant storage and distribution system testing.
- Checks of the main propulsion system helium system.
- Thermal protection system operations.
- Functional tests of the waste containment system.
WORK SCHEDULED:
- Removal of the forward reaction control system on Wednesday.
- APU lube oil service this week.
- Functional tests of the orbital maneuvering system pods.
WORK COMPLETED:
- Replaced a leaking thruster on the right orbital maneuvering
system pod.
STS-48/UARS - DISCOVERY (OV 103) - OPF BAY 1
WORK IN PROGRESS:
- Removal of heat shields.
- Checks of the orbital maneuvering system and reaction control
system motor valves.
- Preparations to deservice lube oil from the auxiliary power
units.
- Main propulsion system leak and functional tests.
- Post flight inspections.
- Thermal protection system operations.
WORK COMPLETED:
- Removal of STS-39 payloads.
STS- 49 - ENDEAVOUR (OV 105) - VAB High Bay 2
WORK IN PROGRESS:
- Preparations to remove the tail cone by the end of this week.
- Installing access to the forward, mid and aft sections of the
orbiter.
- Removal of ferry flight fixtures.
STS-43 SOLID ROCKET BOOSTERS - VAB HIGH BAY 1
WORK IN PROGRESS:
- Mating the left forward motor segment to the stack.
- Joint closeouts.
WORK SCHEDULED:
- Stacking the left forward assembly/nose cone to the booster.
- Stacking the right aft segment to the launch platform on
Thursday.