[sci.space.shuttle] Shuttle Status for 05/16/91

yee@trident.arc.nasa.gov (Peter E. Yee) (05/18/91)

          KSC SHUTTLE STATUS REPORT - THURSDAY, MAY 16, 1991 - 10 AM


           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - PAD 39-B
                                   LAUNCH - MAY 22

          WORK IN PROGRESS:
          - Pressurizing Columbia's hypergolic propellant tanks.
          - Pad will be reopened later today.
          - Launch countdown preparations.
          - Closeouts of the aft compartment.
          - Closeouts of the solid rocket boosters.

          WORK SCHEDULED:
          - Installing the doors on the aft compartment for flight Friday.
          - Start launch countdown 5 p.m. EDT Saturday.
          - STS-40 crew arrives 1:30 p.m. Sunday.
          - Launch at 8 a.m. EDT Wednesday, May 22.

          WORK COMPLETED:
          - Final ordnance installation.

                     STS-43/TDRS - ATLANTIS (OV 104) - OPF BAY 2

          WORK IN PROGRESS:
          - Leak and functional tests of the water spray boilers.
          - Hot lube oil flush of the auxiliary power units.
          - Power reactant storage and distribution system testing.
          - Checks of the main propulsion system helium system.
          - Thermal protection system operations.
          - Functional tests of the waste containment system.
          - Installation of the landing gear flight wheels.
          - Tests of the orbiter's flight control system.

          WORK SCHEDULED:
          - Installation of the external tank umbilical  door  hinge  hous-
          ings.
          - APU lube oil service this week.
          -  Installation  of the three Shuttle main engines beginning Sun-
          day.
          - Functional tests of the orbital maneuvering  system  pods  next
          week.

          WORK COMPLETED:
          - Leak and functional tests of the auxiliary power units.
          - Installation of the brakes.


                    STS-48/UARS - DISCOVERY (OV 103) - OPF BAY 1

          WORK IN PROGRESS:
          - Replacement of a seal saver for a thruster on the right orbital
          maneuvering system pod.  Thruster was leaking yesterday.  The bay
          is cleared for this operation.
          - Removal of heat shields.
          - Checks of the orbital maneuvering system and  reaction  control
          system motor valves.
          -  Preparations  to  deservice  lube oil from the auxiliary power
          units.
          - Main propulsion system leak and functional tests.
          - Post flight inspections.
          - Thermal protection system operations.
          - Preparations to offload residual hypergolic propellants.
          - Shuttle main engine drying operations.


                    STS- 49 - ENDEAVOUR (OV 105) - VAB High Bay 2

          WORK IN PROGRESS:
          - Preparations to remove the tail cone by the end of this week.
          - Installing access to the forward,  mid and aft sections of  the
          orbiter.
          - Removal of ferry flight fixtures.
          -  Preparations  to  briefly  power up the vehicle using a ground
          power supply to allow repressurization  of  the  main  propulsion
          system.


                    STS-43 SOLID ROCKET BOOSTERS - VAB HIGH BAY 1


          WORK IN PROGRESS:
          - Mating the right aft booster to the launch platform.
          - Joint closeouts.

          WORK SCHEDULED:
          - Stacking the right aft center segment this weekend.

          WORK COMPLETED:
          - Stacked the left forward assembly yesterday. This completes the
          left solid rocket booster.