[sci.space.shuttle] Shuttle status 5/22/91

ejbehr@rs6000.cmp.ilstu.edu (Eric Behr) (05/24/91)

 KSC SHUTTLE STATUS REPORT - WEDNESDAY, MAY 22, 1991 - 11:30 AM

  STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - PAD 39-B
              LAUNCH - POSTPONED UNTIL LATE NEXT WEEK


 WORK IN PROGRESS:
 - Preparations to replace the multiplexer demultiplexer (MDM),  9
 cryogenic  propellant temperature transducers and general purpose
 computer no. 4.
 - Preparations to disconnect ordnance devices.
 - Removal of lockers in the middeck.
 - Removal of foam from around the temperature transducers.

 WORK COMPLETED:
 - Access to the aft compartment.
 - Offloaded liquid hydrogen  and  liquid  oxygen  reactants  from
 Columbia's onboard storage tanks.

 WORK SCHEDULED:
 - Disconnection of ordnance devices beginning at 8 p.m.  tonight.
 The pad will be closed during this activity.
 -  Replacement  of  the  main   propulsion   system   temperature
 transducers beginning at midnight.
 - Replacement of the new MDM beginning at midnight.

 FLIGHT CREW:
 -  STS-40 crew Commander Bryan O'Connor,  Pilot Sidney Gutierrez,
 Mission Specialist James  Bagian  and  Rhea  Seddon  and  Payload
 Specialist  Millie Hughes-Fulford departed KSC at about 9:30 a.m.
 enroute  to  Houston.  Mission  Specialist  Tamara  Jernigan  and
 Payload Specialist Drew Gaffney are planning to return to Houston
 tomorrow.

            STS-43/TDRS - ATLANTIS (OV 104) - OPF BAY 2

 WORK IN PROGRESS:
 - Cycles of the external tank doors.
 - Thermal protection system operations.
 - Potable water servicing.
 - Water spray boiler leak and functional tests.
 - Main engine and main propulsion system tests.

 WORK COMPLETED:
 - Installation of the four external tank umbilical door housings.
 - Installation of the three shuttle main engines.

 WORK SCHEDULED:
 - External tank door functional test later this week.


           STS-48/UARS - DISCOVERY (OV 103) - OPF BAY 1

 WORK IN PROGRESS:
 - Work in the midbody.
 - Preparations to remove the three shuttle main engines.
 - Thermal protection system operations.
 - Inspections of the orbiter's hydraulic system.
 - Tests of the Ku-band antenna.

 WORK COMPLETED:
 - Removal of auxiliary power unit no. 3.
 - Removed nine main propulsion system temperature transducers for
 x-rays.

 WORK SCHEDULED:
 - Removal of the three shuttle main engines next week.


           STS-49 - ENDEAVOUR (OV 105) - VAB HIGH BAY 2


 WORK IN PROGRESS:
 - Purges of the freon coolant loop.
 - Installation of platforms in the midbody and aft compartment.

 WORK COMPLETED:
 - Removal of the tail cone.




AFTERNOON SHUTTLE STATUS 5-22-91


          KSC SHUTTLE STATUS - WEDNESDAY, MAY 22 4 P.M.

                        AFTERNOON UPDATE


   STS-40 - COLUMBIA/SPACELAB LIFE SCIENCES - LAUNCH PAD 39-B



     KSC processing teams are continuing  work  on  a  processing
schedule which could lead to launch of Columbia on Saturday, June
1.  The two-hour launch window opens at 8 a.m.  EDT. Preparations
are  in  work  to  replace  the   nine   propellant   temperature
transducers,  the  multiplexer demultiplexer (MDM) and the no.  4
general purpose computer.

     Workers are scheduled to disconnect ordnance devices from  8
p.m.  to  midnight  tonight.  The  pad will be closed to all non-
essential personnel during this operation.

     Replacement of all components is scheduled to begin at  mid-
night  tonight  after the pad has been reopened and will continue
through tomorrow.  Retest of  the  transducers  and  the  GPC  is
scheduled  to  complete by tomorrow afternoon.  Retest of the MDM
requires more time and is scheduled to continue through Saturday.

     Launch countdown preparations will begin Saturday.  Ordnance
devices  will be reconnected and closed out for flight next week.
The countdown is scheduled to begin Tuesday at 5  p.m.  with  the
countdown clock at the T-43 hour mark.

-- 
Eric Behr, Illinois State University, Mathematics Department
Internet: ejbehr@rs6000.cmp.ilstu.edu    Bitnet: ebehr@ilstu