[sci.space.shuttle] Shuttle Status Report 5/28/91

ejbehr@rs6000.cmp.ilstu.edu (Eric Behr) (05/29/91)

KSC SHUTTLE STATUS REPORT - TUESDAY, MAY 28, 1991 - 10 AM

 STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - PAD 39-B
                         LAUNCH - JUNE 1

WORK IN PROGRESS:
- Preparations to begin  the  launch  countdown  at  9  p.m.  EDT
tonight at the T-43 hour mark.
- Closeouts of the aft compartment.
- Removing protective covers from components in the aft.
- Final inspections of the aft compartment.
- Closeouts of the solid rocket boosters.

WORK COMPLETED:
- Retest of the new multiplexer demultiplexer (MDM).
-   Replacement  of  the  six  cryogenic  propellant  temperature
transducers and three plugs in the liquid hydrogen 12-inch  feed-
lines.
- Successful leak tests of the temperature transducers and of the
plugs.
- Retest of the newly installed general purpose computer.
- Reconnection and retest of ordnance devices.

WORK SCHEDULED:
- Flight crew arrival at KSC scheduled 3 p.m. tomorrow.
- Launch at 8 a.m.  EDT Saturday, June 1. Launch window closes at
10 a.m. EDT.

WEATHER FORECAST:
- Probability of having acceptable weather at 8 a.m.  Saturday is
80 percent.  For the overall window, there is a 95 percent chance
of being within launch weather commit criteria.

           STS-43/TDRS - ATLANTIS (OV 104) - OPF BAY 2

WORK IN PROGRESS:
- Cycles of the external tank doors.
- Thermal protection system operations.
- Main engine and main propulsion system tests.
- Preparations to install the forward reaction control system.

WORK COMPLETED:
- Potable water servicing.
- Auxiliary power unit lube oil servicing.

WORK SCHEDULED:
- External tank door functional test.
- Nose wheel steering tests.
- Brake anti-skid tests.


          STS-48/UARS - DISCOVERY (OV 103) - OPF BAY 1

WORK IN PROGRESS:
- Work in the midbody.
- Preparations to remove the three shuttle main engines.
- Thermal protection system operations.
- Main engine flight readiness test.
- Preparations to check the forward reaction control system.


          STS-49 - ENDEAVOUR (OV 105) - VAB HIGH BAY 2

WORK IN PROGRESS:
- Purges of the freon coolant loop.
- Installation of platforms in the midbody and aft compartment.


          STS-43 SOLID ROCKET BOOSTERS - VAB HIGH BAY 1

WORK IN PROGRESS:
- Closeouts of the solid rocket boosters.
- Routing cables for the boosters.


-- 
Eric Behr, Illinois State University, Mathematics Department
Internet: ejbehr@rs6000.cmp.ilstu.edu    Bitnet: ebehr@ilstu