[sci.space.shuttle] KSC Status Reports 6/13-17

ejbehr@rs6000.cmp.ilstu.edu (Eric Behr) (06/19/91)

Sorry about the delay - I could't download anything yesterday, and the
Spacelink files were behind schedule as well. E.


------



  KSC SHUTTLE STATUS  -  THURSDAY, JUNE 13, 1991  -- 9:00 a.m.
_________________________________________________________________


         STS-40/SLS-1  -  COLUMBIA (OV 102)  -  ON ORBIT

WORK SCHEDULED:
*  Landing at Edwards Air Force Base, Calif. currently assessed
   for about 11:39 a.m. EDT, Friday, June 14.
*  A two day ferry flight from Dryden Flight Research Facility to
   KSC is expected to begin June 20 with arrival at KSC June 21.


        STS-43/TDRS-E  - ATLANTIS (OV 104)  -  OPF Bay 2
                       LAUNCH JULY\AUGUST

WORK IN PROGRESS:
*  Aft bay closeouts
*  Mid-body closeouts
*  Preparations for final payload bay cleaning
*  Pad 39-A preparations for receiving payload

WORK COMPLETED:
*  Aerosurface cycling operations
*  Special bulb seal inspections
*  Orbiter hydraulic operations
*  Structural leak checks

WORK SCHEDULED:
*  Final payload bay door closing
*  TDRS-E payload to be delivered to pad 39-A (Monday)
*  Rollover to VAB targeted for mid-day Wednesday, June 19


        STS-48/UARS  --  DISCOVERY (OV 103)  -  OPF BAY 1
                    LAUNCH SEPTEMBER/OCTOBER

WORK IN PROGRESS:
*  OMS system functional checks
*  On board fuel cell system tests
*  Water Spray Boiler 48 hour decay checks
*  Landing gear functional tests

WORK COMPLETED:
*  Main propulsion system checks
*  Deployment of remote manipulator system to vertical
*  Hydraulic and flight control inspections in aft compartment

WORK SCHEDULED:
*  Main engine controller checkouts
*  Auxiliary Power Unit leak and functional tests


       STS-49  --  ENDEAVOUR (0V 105)  --  VAB High Bay 2

WORK IN PROGRESS:
*  17 inch disconnect checks
*  Main propulsion system checks
*  Thermal Protection System work

WORK COMPLETED:
*  Removal of 2 inch and 4 inch liquid hydrogen lines

WORK SCHEDULED:
*  Installation of 17 inch disconnect
*  Endeavour will remain in the VAB until Discovery (OV-103) is
   rolled to the VAB for stacking operations in about 5 weeks.


 STS-43 EXTERNAL TANK/SOLID ROCKET BOOSTERS  --  VAB High Bay 1

WORK IN PROGRESS:
*  Electrical mates and checkouts
*  Strut closeouts
*  Foaming operations




   KSC SHUTTLE STATUS  -  FRIDAY, JUNE 14, 1991  -- 9:30 a.m.
_________________________________________________________________


         STS-40/SLS-1  -  COLUMBIA (OV 102)  -  ON ORBIT

WORK SCHEDULED:
*  Landing at Edwards Air Force Base, Calif. currently assessed
   for about 11:39 a.m. EDT, today.
*  A two day ferry flight from Dryden Flight Research Facility to
   KSC is expected to begin June 20 with arrival at KSC June 21.


        STS-43/TDRS-E  - ATLANTIS (OV 104)  -  OPF Bay 2
                       LAUNCH JULY\AUGUST

WORK IN PROGRESS:
*  Aft bay closeouts
*  MADS recorder checks
*  Payload bay final cleaning
*  Helium bottle decay checks
*  Pad 39-A preparations for receiving payload
*  TDRS-E payload to be installed in canister tonight

WORK COMPLETED:
*  Mid-body inspections and closeouts
*  Preparations for final payload bay cleaning
*  Special bulb seal inspections complete and good
*  Orbiter hydraulic operations

WORK SCHEDULED:
*  Final payload bay door closing
*  Rollover to VAB targeted for mid-night Tuesday night
*  TDRS-E payload to be delivered to pad 39-A (Monday)



        STS-48/UARS  --  DISCOVERY (OV 103)  -  OPF BAY 1
                    LAUNCH SEPTEMBER/OCTOBER

WORK IN PROGRESS:
*  Auxiliary Power Unit leak and functional tests
*  On board fuel cell system tests
*  Water Spray Boiler 48 hour decay checks
*  Landing gear functional tests

WORK COMPLETED:
*  OMS system functional checks
*  Main propulsion system checks
*  Hydraulic and flight control inspections in aft compartment

WORK SCHEDULED:
*  Main engine controller checkouts

       STS-49  --  ENDEAVOUR (0V 105)  --  VAB High Bay 2

WORK IN PROGRESS:
*  17 inch disconnect checks
*  Main propulsion system checks
*  Thermal Protection System work
*  Ammonia boiler installation
*  Flash evaporator connections

WORK SCHEDULED:
*  Installation of 17 inch disconnect



 STS-43 EXTERNAL TANK/SOLID ROCKET BOOSTERS  --  VAB High Bay 1

WORK IN PROGRESS:
*  Strut closeouts
*  Foaming operations
*  Preparations for orbiter mating

WORK COMPLETED:
*  SRB ordnance operations
*  Mechanical and electrical mates

WORK SCHEDULED:
*  Orbiter mating operations
*  Rollout to pad 39-A targeted for June 24.


 

KENNEDY SPACE CENTER -  SHUTTLE STATUS - MONDAY, JUNE 17, 1991

     STS-43/ATLANTIS OV-104/TDRS-E  OPF BAY 2


WORK IN PROGRESS:

     Orbiter T-0 Disconnects
     Tile Waterproofing
     Weight & Center of Gravity Determination

     Installation of IUS/TDRS in Pad A Payload Changeout Room
     Solid rocket booster mechanical closeouts


WORK SCHEDULED:

     Placement of Atlantis on Orbiter Transport Vehicle on
Tuesday
     Atlantis rollover to VAB transfer isle between 11 p.m. and
12 Midnight on Tuesday

     VAB: solid rocket booster inspections


WORK COMPLETE:

     Payload bay cleaning is complete
     Payload bay doors are closed
     Aft main engine compartment is closed out
     Crew compartment leak test complete
     Payload bay leak test complete
     Aft main engine compartment leak test complete
     Orbiter power down complete
     IUS/TDRS arrived atop Pad A at 5:20 a.m.



     STS-48/Discovery OV-103/UARS  OPF Bay 1


WORK IN PROGRESS

     Payload bay reconfiguration
     Orbiter midbody reconfiguration
     Closeout work for payload bay door radiators
     Installation of brakes
     Auxliary power unit leak and functional check
     Powered down electrical work
     Fuel cell system testing
     OMS pod check out
     OMS system leak checks

WORK SCHEDULED

     Checkout of waste water nozzle and dump system
     PRSD system closeouts

WORK COMPLETED

     Auxiliary power unit leak and functional checks
     Hydraulic system inspections
     Waste containment system installed




STS-49/Endeavour OV-105/Intelsat Reboost  VAB High Bay 2


WORK IN PROGRESS

     Thermal Protection System tile work

WORK SCHEDULED

     Flight instrumentation checkout

WORK COMPLETED

     Ammonia Boiler installation
     Flash Evaporator installation


-- 
Eric Behr, Illinois State University, Mathematics Department
Internet: ejbehr@rs6000.cmp.ilstu.edu    Bitnet: ebehr@ilstu