KENNEDY SPACE CENTER - SHUTTLE STATUS - MONDAY, JUNE 17, 1991
STS-43/ATLANTIS OV-104/TDRS-E OPF BAY 2
WORK IN PROGRESS:
Orbiter T-0 Disconnects
Tile Waterproofing
Weight & Center of Gravity Determination
Installation of IUS/TDRS in Pad A Payload Changeout Room
Solid rocket booster mechanical closeouts
WORK SCHEDULED:
Placement of Atlantis on Orbiter Transport Vehicle on
Tuesday
Atlantis rollover to VAB transfer isle between 11 p.m. and
12 Midnight on Tuesday
VAB: solid rocket booster inspections
WORK COMPLETE:
Payload bay cleaning is complete
Payload bay doors are closed
Aft main engine compartment is closed out
Crew compartment leak test complete
Payload bay leak test complete
Aft main engine compartment leak test complete
Orbiter power down complete
IUS/TDRS arrived atop Pad A at 5:20 a.m.
STS-48/Discovery OV-103/UARS OPF Bay 1
WORK IN PROGRESS
Payload bay reconfiguration
Orbiter midbody reconfiguration
Closeout work for payload bay door radiators
Installation of brakes
Auxliary power unit leak and functional check
Powered down electrical work
Fuel cell system testing
OMS pod check out
OMS system leak checks
WORK SCHEDULED
Checkout of waste water nozzle and dump system
PRSD system closeouts
WORK COMPLETED
Auxiliary power unit leak and functional checks
Hydraulic system inspections
Waste containment system installed
STS-49/Endeavour OV-105/Intelsat Reboost VAB High Bay 2
WORK IN PROGRESS
Thermal Protection System tile work
WORK SCHEDULED
Flight instrumentation checkout
WORK COMPLETED
Ammonia Boiler installation
Flash Evaporator installation