baalke@mars.jpl.nasa.gov (Ron Baalke) (10/10/89)
GALILEO DAILY REPORT 6 OCTOBER 1989 General Spacecraft CDS memory loading on logic power was completed successfully on 3 and 4 October. On 4 October, the spacecraft was turned on so as to be able to verify L-20 min discrete from the IUS after the changeout of the IUS computer A. In addition, both the spacecraft and the IUS performed stray voltage tests to the spacecraft to insure the super zip detonator block connector pins have no voltage while the spacecraft and the IUS is on. In the early morning of 5 October, the super zip detonator block firing cables were connected to the spacecraft and FTK checks were performed thus completing all of the spacecraft pryotechnic preflight activities. In the early morning of 6 October, closeout operations were performed; PWS dipole antennas were installed, the science purge was transferred to the T-0 source via the 4 way valve. The cabling to the spacecraft from the support equipment simulated RTG power supply was disconnected and the final spacecraft cleanliness inspection and cleaning was performed. The only remaining mechanical activity is the disconnection and capping of the carry-on umbilicals, and the installation of the related thermal blanket. LCET LCET #1 CDS ground support computer was exercised to assure that spacecraft memory loading was functioning; memory loading by the computer was successful. RTG Cooling Loop Vacuum drying of the payload portion of the cooling loop is still on-going; results to date indicate that the "dry" specifications will be satisfied prior to servicing the loop with water/alcohol. STS IUS: On 4 October, the IUS went into their ordnance operations at the completion of the computer A replacement and retest. The ordnance operations were reported as having been completed satisfactorily. Schedule Discussion and Assessment As discussed in the report of 4 October, a new payload schedule has been issued. The highlights of the schedule are as follows: 4 Oct-5 Oct IUS/GLL closeout operations 6 Oct 0800-1600 RTG preparations for transfer to Pad 1000-1400 Payload contamination inspection and cleaning 6 Oct-7 Oct 1600-0200 Reconfigure PGHM for RTG operations 7 Oct 0200-0500 JPL Launch Complex 39-B preparations for RTG operations 1700-1900 Transport RTGs to Pad B 7 Oct-8 Oct 1900-0700 Install RTGs in spacecraft and air bath operations 8 Oct 0400-1600 Galileo Launch Conditioning 0600-2100 RTG Coolant Servicing Functional Test 9 Oct 0400-0600 Disconnect Galileo carry-on umbilicals and final closeout 9 Oct 0800 Launch Countdown start L-76 hr T-43 hr
baalke@mars.jpl.nasa.gov (Ron Baalke) (10/10/89)
GALILEO DAILY REPORT 9 OCTOBER 1989 NOTE: This report covers the activities of 6-9 October General Spacecraft The RTGs were installed on 7 and 8 October. Spacecraft Launch Conditioning was subsequently performed and completed successfully. Final spacecraft closeouts have been performed. The spacecraft is now in a complete ready state for launch; the discrete from the IUS at L-20 min. is the only remaining prelaunch command to be sent. STS IUS: The only scheduled operation was the open circuit voltage checks on the flight batteries. This was completed successfully on 7 October. The PLBD (payload bay doors) were closed at approximately 12:45 p.m. on 9 October. Details Spacecraft At 0200 hours on 7 October, JPL performed the final preparations for RTG installations at Launch Complex 39B. During the removal of the end-blocks (used for testing the cooling loop when the RTGs are not installed) from the ACS (Airborne Cooling System), a JPL technician alertly detected a foreign object in the supply side to the RTG cooling line. Approximately 40 psi of nitrogen pressure was used in an unsuccessful attempt to clear the line. The pressure was subsequently reduced to approximately 20 psi and hemostats were used to remove the debris which was later identified as a piece of foam porous pad. The foam pads are used to temporarily seal the lines from contamination any time a joint of the system plumbing is broken. This is the same type of material previously reported as the cause of the earlier RTG cooling loop problem (see Report #78). Meetings were held between JPL and Lockheed engineers/managers. It was decided to perform a boroscope examination of the sharp bends of the cooling system immediate interface to the RTG. Test results showed the bends to be clean. Based on these results and the fact that approximately equal nitrogen flow was obtained through each RTG branch with a nitrogen flow, it was decided to proceed with the installation of the RTGs without any additional action. The RTGs were delivered to the base of the launch pad at approximately 6:30 p.m. 7 October. The first RTG was hoisted to the PCR (Payload Changeout Room) but operations were then interrupted for approximately 1 1/2 hours by lightning storms. The -x RTG was then installed without any problems except during the mating of the PRD (pressure release devices) to the RTGs; the screw lengths were too long and two additional washers had to be installed on each of the two screws. The second RTG was then hoisted and installed without any problems; washers were also installed on the PRD screws. The operation was completed at approximately 2:30 a.m. on 8 October. At 0400 hours on 8 October, during the process of applying the planned short to the -x RTG by an external S.E. box, it was discovered that the meter went to approximately 25 volts instead of near zero. The spare shorting box was then used and the appropriate reading obtained. The problem was later found to be in the meter. The process for applying RTG power to the spacecraft continued without any further problems. At the conclusion of powering the spacecraft from the RTGs, at approximately 0610 hours on 8 October, the conditioning of the spacecraft for launch commenced. Launch conditioning was completed at approximtely 6:00 p.m. on 8 October. Memory compares of the spacecraft memory contents to the memory load have been completed and it has been reported as being successful at approximately 0300 hours on 9 October. The PRD safe pins have been removed on 9 October and the carry-on umbilicals disconnected. The spacecraft portion of the carry-on umbilical connectors have been capped and the related thermal blanket installed. The PGHM and RTG installation platforms have been placed in a configuration that allowed the orbiter PLBD (payload bay doors) to be closed; the PLBDs were closed at approximately 12:30 p.m. on 9 October. Schedule Discussion and Assessment Launch is still scheduled for 12 October at 1:29 p.m. EDT.
baalke@mars.jpl.nasa.gov (Ron Baalke) (10/11/89)
GALILEO DAILY REPORT 10 OCTOBER 1989 General Spacecraft The spacecraft is in is launch ready state as previously reported. The spacecraft continues to be monitored 24 hours a day both at KSC and at Pasadena. There have been no problems to date. LCET LCET #1 was returned to the VPF (Vehicle Processing Facility) area on 9 October. All communications, power, and power cables have been installed. LCET #1 is now operational and monitoring the spacecraft telemetry derived from the composite telemetry through the T-0 cabling. Telemetry alarms matching those of the MTS have been inserted and are operational. This provides a backup capability in case the lines to JPL become inoperative. Schedule Discussion and Assessment The launch at this time is still scheduled for 12 October at 1:29 p.m. EDT. Ron Baalke (818) 541-2341 Jet Propulsion Lab M/S 301-355 4800 Oak Grove Dr. Pasadena, CA 91109
baalke@mars.jpl.nasa.gov (Ron Baalke) (10/13/89)
GALILEO DAILY REPORT 11 OCTOBER 1989 SPECIAL ANNOUNCEMENT: 17 October at 12:57 p.m. EDT is the new launch date for Galileo. General Spacecraft The spacecraft is still in its launch ready state and is being monitored constantly both at KSC and at Pasadena. A PF/R was opened, analyzed, and dispositioned on the attachment of the PRDs (Pressure Release Device) to the RTGs. LCET LCETs #1 and #2 are both being manned around the clock when spacecraft telemetry analysis is in process. Details Spacecraft The spacecraft continues to operate satisfactorily from power supplied by the RTGs. However, temperature control engineering has requested that the orbiter air conditioning to the spacecraft be raised from 52 deg F to 58 deg F. The basis of this request was the RPM temperature which is at its lower acceptable limit as specified in the launch commit criteria. The orbiter temperature was raised as per JPL's request on the evening of 10 October. Appropriate paper is in process that will allow the inlet temperature to be varied from 48 deg F to 60 deg F. This in turn will allow for any future adjustment as a normal operation of the prelaunch activities. As reported on 9 October, during the mating of the PRD (Pressure Release Device) to the RTG two additional washers were installed on each of the four screws used to attach the PRDs to each of the RTGs. Questions were raised on the action taken, that is, the installation of the washers. PF/R 54340 was opened to document the concern expressed by General Electric. Subsequent analysis was made on the overall incident. The primary points were: 1) that during the insertion of the screws the engagement of the screws into the insert locking mechanism was misinterpreted as the screw bottoming out, 2) two washers were added to reduce the gap which in turn reduced the amount of screw engagement in the insert locking mechanism, 3) both JPL and GE engineers agreed that the last one turn into the locking mechanism was required, 4) the JPL technician, that did the hands-on work, and the engineer, that witnessed the work, agreed that two screw turns into the locking element were achieved, 5) that there would be no impact to the mission if one screw backed out. Additional analysis was done at JPL, and after review of the total picture, the Project Manager declared that no further action was necessary; in short, that the attachment of the PRDs to the RTGs was satisfactory. Schedule Discussion and Assessment It was announced this afternoon that the new launch date is 17 October at 12:57 p.m. EDT. The count will be resumed on Monday, 16 October at L-19 hours at 5:57 p.m. EDT. Shortly after the countdown is picked up the IUS is scheduled to be powered for its final prelaunch conditioning and checks. Ron Baalke (818) 541-2341 Jet Propulsion Lab M/S 301-355 4800 Oak Grove Dr. Pasadena, CA 91109
baalke@mars.jpl.nasa.gov (Ron Baalke) (10/17/89)
GALILEO DAILY REPORT 16 OCTOBER 1989 General NOTE: This report covers the activities of 14-16 October Spacecraft The spacecraft still remains in its launch ready state. The next spacecraft event will occur at L-20 min when a command is received from the IUS to turn on the DMS (Data Management System) and remove the bias from the HIC and EPD science instruments. There has been only one additional CDU (Command Detector Unit) subcarrier lock indications since 11:57 p.m. on 12 October. This occurred today at 11:12 a.m. There is no JPL concern regarding these locks; they do have a finite probability of occurring and more so in presence of a commercial carrier near the center band of the receiver. Spacecraft telemetry has been stable during this period without any changes in temperatures, etc. LCET LCET #1 and #2 are in a ready state to support the pre launch and post launch activities up to and including acquisition by the DSN (Deep Space Network). STS A L-2 Day status meeting was held at KSC on 15 October. All systems, including the spacecraft, gave their "go" for launch on Tuesday, 17 October. Today, 16 October, the L-1 Day telecon was held between all systems and the astronauts. Again, all systems gave their "go" for launch on tomorrow, Tuesday. "The Galileo spacecraft is ready for launch and has had essentially housekeeping chores during the standdown. Launch is scheduled to occur at the opening of the launch window or at 12:57 p.m. (EDT). The window for tomorrow closes at 1:23 p.m. (EDT)." KSC Public Affairs Office, 16 October 1989 Ron Baalke (818) 541-2341 ext 260 Jet Propulsion Lab M/S 301-355 4800 Oak Grove Dr. Pasadena, CA 91109
baalke@mars.jpl.nasa.gov (Ron Baalke) (10/18/89)
GALILEO DAILY REPORT 17 OCTOBER 1989 General The launch countdown went down to T-5 minutes but due to adverse weather at KSC, which would have affected the return of the Atlantis to the base, it was decided to scrub the launch and retry tomorrow, 18 October. The opening of the launch window is 12:50 p.m. EDT terminating at 1:17 p.m. Retanking of the orbiter is scheduled to occur at 4:00 a.m. EDT on 18 October. Ron Baalke (818) 541-2341 ext 260 Jet Propulsion Lab M/S 301-355 4800 Oak Grove Dr. Pasadena, CA 91109
baalke@mars.jpl.nasa.gov (Ron Baalke) (10/19/89)
GALILEO DAILY REPORT 18 OCTOBER 1989 General STS 34, with Galileo aboard, was launched from KSC at 12:53 p.m. EDT on 18 October 1989. Once in orbit the IUS went through a predeployment checkout. A "Mission Phase 6" error did occur when attempting to lock in the RF link to Sunnyvale through the PI (Payload Integrator), but this was determined to be static on the RF link. The tilt table was then raised up to a 58 degree angle, and Galileo was deployed at a time of 6 hours 21 minutes 23.397 seconds after launch, on the 6th orbit around the earth. The tilt table was then lowered back down to its initial -6 degrees. At about 15 minutes after deployment Atlantis executed a separation burn. Live pictures were then transmitted to Houston control showing the payload bay area and the inside of the shuttle. At 7 hours 21 minutes after launch the 1st stage IUS burn was executed and verified by Sunnyvale. The 2nd stage UIS burn occurred 5 minutes later to place Galileo on an Earth escape velocity of 7.1 miles/sec. The VTR playback of the Galileo deployment was then transmitted to Houston. Debris looking like ice particles was seen to be floating around the shuttle. Houston control questioned the crew about what the debris could be. At 7 hours 46 minutes after launch, the IUS went into a 1st stage spinoff to deploy the RTG and science booms. The 2nd stage IUS spinoff at a rate of 2.9 revolutions/second for the separation of the IUS from Galilio sooned followed. At this point telemetry data were transmitted and recieved by DSN (Deep Space Network). Galileo is expected to arrive at Venus in February 1990 on its first leg of its journey to Jupiter. Ron Baalke (818) 541-2341 ext 260 Jet Propulsion Lab M/S 301-355 4800 Oak Grove Dr. Pasadena, CA 91109
spinkert@pikes.Colorado.EDU (Scott Casto Pinkerton) (10/20/89)
In article <1939@jato.Jpl.Nasa.Gov> baalke@mars.jpl.nasa.gov (Ron Baalke) writes: > The 2nd stage IUS spinoff at a rate of >2.9 revolutions/second for the separation of the IUS from Galilio sooned >followed. Was this correctly printed ?? The IUS spun itself and the payload up to 174 RPM prior to separation ?? That seems like an incredible controls problem to prevent the stack from spinning in a very wide "cone". Also at actual separation, the CG will jump back some 30-40 feet maybe (don't know actual Galileo dimensions) - again sounds like one hell of a controls problem. Was this meant to be 2.9 RPMinutes ??
wilkins@jarthur.Claremont.EDU (Mark Wilkins) (10/21/89)
In article <2832@pikes.Colorado.EDU> spinkert@pikes.Colorado.EDU (Scott Pinkerton) writes: >In article <1939@jato.Jpl.Nasa.Gov> baalke@mars.jpl.nasa.gov (Ron Baalke) writes: >>2.9 revolutions/second for the separation of the IUS from Galilio sooned >>followed. > >Was this correctly printed ?? The IUS spun itself and the payload up to >174 RPM prior to separation ?? That seems like an incredible controls >problem to prevent the stack from spinning in a very wide "cone". Also at >actual separation, the CG will jump back some 30-40 feet maybe (don't know >actual Galileo dimensions) - again sounds like one hell of a controls >problem. Was this meant to be 2.9 RPMinutes ?? Sometime if you ever get the chance watch some of the footage of one of those satellites with an IUS being launched. When STS-26 went up many at our school watched the TDRS deployment and the thing was rotating about one or two times each second during the deployment from the cargo bay. Galileo is (I think) smaller than TDRS and I would not be surprised at 2.9 revolutions per second, especially after the IUS has carried the thing some distance from the shuttle. -- Mark Wilkins
baalke@mars.jpl.nasa.gov (Ron Baalke) (10/31/89)
GALILEO STATUS UPDATE 30 OCTOBER 1989 Galileo is now 2.5 million miles from Earth traveling at 59,845 mph as it slowly drops in towards the orbit of Venus. Its radio transmitter is now operating at 30 watts and its propulsion system has been operated twice in tests and for maintainence purposes. Galileo's atmospheric probe has been checked out last week and its condition is fine. The spacecraft's ion detector was turned on during the latter part of the solar flare and has measured heavy ions in the range of 130 million volts, none of which affected Galileo's electronics. On Wednesday, the spinning of the lower part of the spacecraft where the optical sensors are mounted will be stopped. At present the whole spacecraft is spinning at 2.9 revolutions per minute. The top part of Galileo where controller electronics, power, propulsion, radiation and magnetic field sensors, and radio attennas are located will continue spinning for the duration of the mission. Ron Baalke | (818) 541-2341 x260 Jet Propulsion Lab M/S 301-355 | baalke@mars.jpl.nasa.gov 4800 Oak Grove Dr. | Pasadena, CA 91109 |
baalke@mars.jpl.nasa.gov (Ron Baalke) (11/02/89)
GALILEO WEEKLY STATUS October 30, 1989 This is a weekly Galileo status report. Today, October 30, 1989, the spacecraft is about 2.5 million miles from Earth, and has gone 16.7 million along its 2.4-billion-mile spiral course to Jupiter. Its velocity around the Sun is almost 60,000 mph. All subsystems are working well. Since launch, operators have sent hundreds of real- time commands to the Galileo spacecraft. The S-band transmitter has been switched to 30 watts, and the propulsion system has been exercised twice in maintenance maneuvers (primarily to move oxidizer and fuel along in the plumbing.) The telemetry rate is 7.68 kilobits per second. As of this morning, the spacecraft is spinning at 2.9 rpm around an axis within 1 degree of the Sun line. As Galileo progresses around towards Venus, the Sun angle changes; this is held to less than 14 degrees, by commanded or automatic maneuvers, to assure a shaded spacecraft. The atmospheric entry probe was checked out last Thursday, October 26, and its condition is satisfactory. The imaging system and the near-infrared mapping spectrometer were checked out Friday, with good results. Preparatory activities for various other science instruments are being done, but the only instruments actually turned on and taking data are the magnetometer and the HIC. The heavy ion counter, an engineering instrument modified from parts of a Voyager cosmic-ray sensor, was turned on ten days ago and detected the latter part of the solar flare of October 19. Heavy ions of energies up to 130 MEV (million electron volts) have been detected, but the spacecraft has experienced no single-event upsets (i.e., no ill effects.) Today the star sensor on the spinning section is to be checked out, in preparation for Wednesday's start of dual- spin operations. The lower section of the Galileo spacecraft will be spun in reverse, with electric motors, stopping the rotation and despinning the science scan platform. The first trajectory-correction maneuver, TCM-1, is scheduled, in three instalments, for November 9, 10 and 11. Ron Baalke | (818) 541-2341 x260 Jet Propulsion Lab M/S 301-355 | baalke@mars.jpl.nasa.gov 4800 Oak Grove Dr. | Pasadena, CA 91109 |
yee@trident.arc.nasa.gov (Peter E. Yee) (11/02/89)
To prevent further duplication of work, Ron and I have agreed that Ron will post *all* Galileo status reports and information briefs. I'll do the rest of the NASA postings. -Peter Yee yee@ames.arc.nasa.gov ames!yee
baalke@mars.jpl.nasa.gov (Ron Baalke) (11/08/89)
GALILEO WEEKLY STATUS November 7, 1989 As of 8 a.m. (PST) Tuesday, November 7, 1989, the Galileo spacecraft is 4.16 million miles from Earth, 28.2 million miles along its path to its first gravity assist at Venus. Round-trip light time is almost 45 seconds. Galileo still has 157 million miles to go just to reach Venus; it is reducing that distance at a rate of just over 60,000 mph, increasing slowly as it comes closer to the Sun. Jupiter lies about 2.4 billion miles ahead along the VEEGA trajectory. The spacecraft is spinning at about 3 rpm around an axis pointed a few degrees from the Sun. It is transmitting telemetry at 7.68 kilobits per second; the RTG's are providing about 570 watts of power, 60 watts more than needed at present. The heavy ion counter, an engineering instrument which detects charged particles from the atomic weight of carbon through that of iron, has been seeing at least one every 2/3 second, mostly oxygen. It detected and characterized the recent major solar flare. Last week Galileo's flight team continued checkout, maintenance, and characterization of various elements of the spacecraft. Notable among these was the dual-spin mode, in which a major part of the spacecraft, carrying the scan platform with 4 instruments, the probe and probe relay system and associated electronics, was spun in reverse while the rest of the machine was still spinning at about 3 rpm. This mode, which allows the camera and other remote-sensing instruments to be aimed at planetary targets, was satisfactorily maintained during the 70-minute checkout. The spacecraft was then put back in the all-spin mode for other planned cruise operations. These included sun pointing (moving the spin axis from about 10 down to 1.25 degrees from the Sun line). Before and after this maneuver, the star sensor was given a star map and turned on to determine attitude and spin rate, which it did as planned. An additional propulsion system maintenance sequence was done early Monday. The first trajectory correction maneuver is planned for November 9, 10, and 11; it will change the spacecraft velocity by less than 17 meters per second (about 38 mph). Small axial and lateral thrusters will fire in pulses of about 1-sec duration. Nothing in the mission so far has ruled out the possibility of an asteroid encounter (Gaspra, between the first and second Earth flybys). However, no final decision on asteroid encounters will occur until after the Venus flyby in February, when Galileo's flight team and other project personnel evaluate the post-Venus flight path and the propellant margins at that time. Ron Baalke | (818) 541-2341 x260 Jet Propulsion Lab M/S 301-355 | baalke@mars.jpl.nasa.gov 4800 Oak Grove Dr. | Pasadena, CA 91109 |
baalke@mars.jpl.nasa.gov (Ron Baalke) (11/15/89)
Galileo Status Report 14 November 1989 The first course change maneuver for Galileo was successfully completed last Saturday. The two day maneuver began last Thursday morning at a distance of 28,200,000 miles from Earth, and consisted of a long series of time pulses of Galileo's 2.2 pound thrusters. A shorter continuous period of firing would have overheated the thrusters. The total speed change was 38 mph which will move Galileo closer to its target point near Venus, but changes the arrival time to Venus on February 9th by only a few minutes. During the maneuver, a temperature sensor on one of the thrusters failed. However, in the future the temperature of that thruster can be deduced from nearby thruster readings. Galileo is now 55,162,000 miles from Earth and traveling at 60,807 mph. After gaining momentum from Venus's gravity, Galileo will return to Earth in December next year, use Earth's gravity to loop out to the asteroid belt, and return back to Earth again two years later for a final gravity push to reach Jupiter in December 1995. Several more days of tracking are needed to determine the accuracy of last week's course change. Ron Baalke | baalke@mars.jpl.nasa.gov Jet Propulsion Lab M/S 301-355 | baalke@jems.jpl.nasa.gov 4800 Oak Grove Dr. | Pasadena, CA 91109 |