[sci.space] Payload Summary for 02/08/91

yee@trident.arc.nasa.gov (Peter E. Yee) (02/09/91)

                                   GRO Status Report
                                   Kennedy Space Center
                                   February 8, 1991

          George Diller
          407/867-2468
          FTS 823-2468



          GAMMA RAY OBSERVATORY/STS-37   (Atlantis-April, 1991)

               The Gamma Ray Observatory began its 1-mile trip from the
          Payload Hazardous Servicing Facility to the Vertical Processing
          Facility (VPF) at 5:00 a.m. Thursday morning as scheduled.  It
          arrived at the VPF air lock about one hour later and was moved
          into the high bay at 8:30 a.m.  Work was completed by early
          afternoon to remove the protective covers and the anti-static
          liner over the spacecraft.  Preparations are being made today for
          hoisting the Observatory into the west test cell.  The actual
          crane operation is scheduled for Saturday morning.

               Next week, on Feb. 12 a two-day stand alone Observatory
          functional test will be conducted.  The following week the
          integrated electrical tests are scheudled to start, beginning
          with the Interface Verification Test on Feb. 19 to verify the
          GRO's electrical compatability with the orbiter.   The end-to-end
          test will follow on approximately Feb. 21 to verify
          communications between the Observatory and the Payload Operations
          Control Center at Goddard.   The payload will go to the pad on or
          about Mar. 6.