[sci.space] space news from Jan 28 AW&ST

henry@zoo.toronto.edu (Henry Spencer) (03/11/91)

Amroc proposes Aquila, a four-stage hybrid launcher for Motorola's Iridium
mini-comsat network, claiming 1500lbs to 300nmi at about half the cost of
current alternatives.

ESA declares Ulysses fully operational.

Space insurance rates expected to rise after circa $200M losses on recent
in-orbit satellite failures.

USAF Space Command has set up special data links to get data from missile-
warning satellites directly to Patriot batteries nearly in real time.
This plus other measures to improve communications have boosted warning
time for Scud attacks to nearly 5min from 90-120s.  Warning-satellite
officials say Iraq's Scud tests late last fall were serious blunders,
because they gave the US a priceless opportunity to debug the warning
setup before it was needed in combat.

Final design details have been settled for the field joint of the ASRM.
The new joints are bolted together, the O-rings remain visible as the
joint is mated, and the joint is designed to close up under pressure
rather than opening.  Looking at the diagram, inboard of the bolts the
joint is two flat flanges touching each other, and two O-rings are set
into the surface of the lower flange near the inner edge.  The upper
flange goes to the edge of the lower flange and then turns downward
around it, with a third O-ring set into the outer surface of this lip,
seating against the inner edge of the lower flange.

Another major ASRM design change is careful design of the internal shape
of the fuel so that thrust drops off somewhat for a brief period early
in the flight, eliminating the need for the SSMEs to throttle back during
the period of maximum dynamic pressure.  This eliminates assorted possible
failure modes related to throttle-back and the following throttle-up.
Other changes include a revised casing design that has fewer assembled
parts, one less field joint, welded factory joints, and better steel;
a simpler nozzle design eliminating assorted joints and seals; and a
redesigned igniter.  Finally, a lighter casing, a larger diameter holding
more fuel, and a slightly more energetic fuel give higher thrust, longer
burn, and about 18% more shuttle payload.  An important change unrelated
to the booster design is the shift to highly automated manufacturing,
since each handling step increases the odds of trouble.  [Another aspect
of this, not mentioned, is that the ASRM plant at Yellow Creek will be
NASA-owned, so NASA will be less tied to a single contractor and can
exert more control.]

ASRM still has its critics, however.  Some say the $971M would be better
spent elsewhere, especially on the SSMEs and on incremental improvements
to the existing boosters (since ASRM is still five years away).  There
is the possibility of political pressure to shift money to heavylift
boosters, and concerns about the environmental effects of the rather
"dirty" solid fuels.  Finally, there is still strong skepticism in some
areas about the safety of manned flight on solid boosters, given the
sensitivity to manufacturing flaws and the impossibility of test-firing.
Cost considerations are likely to preclude abandoning SRBs, however.

[That's it for space news in this AW&ST.  They are rather preoccupied
with other current events...  However, here's a *very* interesting bit
from the 15 Feb issue of Science:]

Congress is very interested in the Augustine commission's recommendation
for a heavylift launcher, and there is starting to be specific interest
in one particularly heavylift launcher... the Saturn V!!  Truly, questioned
about the matter, says the plans still exist.  It's pretty obvious, though,
that NASA would really prefer a shuttle-derived launcher.  Congress may
pursue the matter, although there is the obvious problem that tooling is
gone and many subcontractors are gone, so resurrecting the Saturn V would
be costly.
-- 
"But this *is* the simplified version   | Henry Spencer @ U of Toronto Zoology
for the general public."     -S. Harris |  henry@zoo.toronto.edu  utzoo!henry