          KSC SHUTTLE STATUS  -  WEDNESDAY, MARCH 13, 1991  ---  10:30 a.m.
          _________________________________________________________________
 
             STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - VAB HB 3
                               LAUNCH  --  EARLY APRIL
 
          WORK IN PROGRESS:
          *  Orbiter Interface verification tests
          *  Tile step and gap operations near nose cone
          *  SRB battery checks
          *  Vehicle frequency response test
          *  Preparations for rollout to pad 39-B
          *  Platform retractions in VAB
          *  GRO integration into Payload Changeout Room at pad B
               (arrived at pad at 4:00 a.m. today)
 
          WORK COMPLETED:
          *  Liquid oxygen and liquid hydrogen monoball electrical
               connections
          *  Leak checks of main propulsion system
          *  Hydraulic circulation and sample tests
          *  Removal of debris shields
          *  SRB APU checks
 
          WORK SCHEDULED:
          *  Rollout to pad 39-B targeted for 12:01 a.m. Friday
          *  Following rollout to pad:
             -  APU hot fire (Friday)
             -  Payload installation into orbiter payload bay (Sunday)
             -  Helium Signature test (Monday)
             -  Terminal Countdown Demonstration Test (T-0 on Wednesday)
 
 
                   STS-39/DoD  -  DISCOVERY (OV 103)  -  VAB HB 1
                          LAUNCH  --  LATE APRIL, EARLY MAY
 
          WORK IN PROGRESS:
          *  Lifting orbiter to transfer aisle
 
          WORK COMPLETED:
          *  Installation of aft access doors
          *  Sling lift and build up and orbiter demate operations
 
          WORK SCHEDULED:
          *  VAB orbiter hydraulic operations
          *  Replace flight nose wheel tire with rollover wheel tire in
               VAB transfer aisle
          *  Rollover to Orbiter Processing Facility bay 2 Thursday morning
               at 8:30 a.m.
          *  Replace ET door hinge mechanism with one from Endeavour once
               in the Orbiter Processing Facility
 
 
          STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102)  -  OPF BAY 1
 
                                   LAUNCH  -  MAY
 
 
          WORK IN PROGRESS:
          *  Water Spray boiler servicing
          *  Auxiliary power unit leak and functional tests
          *  Mid-body operations
          *  Thruster inspections
 
          WORK COMPLETED:
          *  External tank umbilical door drive mechanism removed and
               shipped to Rockwell plant in California Saturday (due back
               at KSC end of March)
          *  Freon loop reservicing operations
          *  APU number 2 fuel line connections
          *  APU lube hot oil flush
 
          WORK SCHEDULED:
          *  OMS/FRCS functional and deservicing operations
          *  Solid rocket booster stacking operations in VAB following
               STS-37 rollout operations

      ___    _____     ___
     /_ /|  /____/ \  /_ /|      Ron Baalke         | baalke@mars.jpl.nasa.gov
     | | | |  __ \ /| | | |      Jet Propulsion Lab | 
  ___| | | | |__) |/  | | |___   M/S 301-355        | Change is constant. 
 /___| | | |  ___/    | |/__ /|  Pasadena, CA 91109 | 
 |_____|/  |_|/       |_____|/                      |