[sci.space] Shuttle Status for 03/21/91

baalke@mars.jpl.nasa.gov (Ron Baalke) (03/22/91)

          KSC SHUTTLE STATUS REPORT - THURSDAY, MAR. 21, 1991 - 10  a.m.
 
             STS-37/GAMMA RAY OBSERVATORY - ATLANTIS (OV 104) - PAD 39-B
                                   LAUNCH - APRIL
 
          WORK IN PROGRESS:
          - Interface verification tests between the orbiter and the  Gamma
          Ray Observatory payload.
          - Inspections of orbiter components in the aft compartment due to
          water intrusion.
          -  Preparations  for  loading hypergolic propellants into the or-
          biter.
          - Launch Readiness Review.
 
          WORK COMPLETED:
          - Countdown Demonstration Test.
 
          WORK SCHEDULED:
          - Loading hypergolic propellants into the orbiter beginning  late
          tomorrow.
          - Flight Readiness Review March 26-27.
 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 2
                           LAUNCH - LATE APRIL, EARLY MAY
 
          WORK IN PROGRESS:
          - Rigging of the right hand external tank door hinge housings and
          cycling of the doors to retest.
          - Thermal protection system operations.
          - Functional tests of the external tank doors.
 
          WORK SCHEDULED:
          - Roll to the Vehicle Assembly Building Monday.
 
           STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - OPF BAY 1
                                    LAUNCH - MAY
 
          WORK IN PROGRESS:
          - Testing connections for the payload.
          - Electrical connections of space shuttle main engines.
          - Preparations to service the ammonia boilers.
          - Orbital maneuvering system pod functional tests.
          - Thermal protection system operations.
          - Preparations to replace the S-band antenna.
 
          WORK SCHEDULED:
          - Installation of the Spacelab Life Sciences payload into the or-
          biter this weekend.
 
          WORK COMPLETED:
          - Installation of the three main engines.
 
 
                         STS-40 SOLID ROCKET BOOSTERS - VAB
 
               Optical  alignment  of  the  hold  down  posts on the mobile
          launcher platform is in progress.  The left and right aft  skirts
          have been removed from the mobile launcher platform. Earlier this
          week,  gauges attached to the aft skirts and hold down posts gave
          readings about the loads that are not understood.  The concern is
          that  the  posts  are  not  aligned properly.  The aft skirts are
          scheduled to  be restacked on Saturday. Schedule impacts are cur-
          rently being assessed.

      ___    _____     ___
     /_ /|  /____/ \  /_ /|      Ron Baalke         | baalke@mars.jpl.nasa.gov
     | | | |  __ \ /| | | |      Jet Propulsion Lab | 
  ___| | | | |__) |/  | | |___   M/S 301-355        | Change is constant. 
 /___| | | |  ___/    | |/__ /|  Pasadena, CA 91109 | 
 |_____|/  |_|/       |_____|/                      |